GC1 # 19424

Gas Company:
WINDER NATURAL GAS SYSTEM, CITY OF
Title:
Sikes Rd
Home State:
Georgia
Home County:
Fulton
Certificate Number:
Construction Type:
New Construction
Submitted By:
WINDER NATURAL GAS SYSTEM, CITY OF
Submission Date:
2026-03-19T09:06:14.6984425
Pipeline Length 1:
10,000 feet
Pipeline Diameter:
3
Pipeline Type:
Plastic
Pressure:
55 lbs psig
Start Date:
2026-03-19T00:00:00
End Date:
2026-04-30T00:00:00
Affected Counties 2:
Oconee
Receipt Number:
2fff2ecd-7f6e-4c29-9517-aa78f6c39fcf
Status:
Accepted
Comments:
Installing 4'' PE gas main to serve new project on Sikes Rd.
Estimated Pipeline Length:
1 Pipeline Length is submitted by the user.
2 Affected Counties are the counties construction is taking place.
3 Estimated Pipeline Length is calculated by the system based on the pipeline drawn on the map.